Deadlines for Disaster: County Takes 13 Steps
- Share via
Three years ago, the Southern California Earthquake Preparedness Project developed a 39-step plan to get the county ready for an earthquake. In February, 1987, the Board of Supervisors directed that $3 million be spent to implement the following 13 steps as a “first phase.”
1. Structural survey of all county-owned buildings built before 1950 and likely to be vulnerable. Cost: $220,000. Deadline: February, 1988. Status: Ready soon.
2. Plan for all county buildings to have enough fire extinguishers train employees to use them. Cost: $31,557. Deadline: February, 1992. Status: Complete.
3. Plan for all county buildings to have an emergency generator to operate lights, phones, radios, computers and other vital equipment. Cost: $1,627,164. Deadline: February, 1997. Status: Unfunded.
4. Plan for emergency communication system between all county agencies and facilities as backup to phone system. Cost: $155,500. Deadline: August, 1987. Status: Complete.
5. Plan to properly secure radios, computer terminals, antennas and other vital communication equipment. Cost: $267,000. Deadline: August, 1987. Status: Complete.
6. Plan to protect all vital records and databases. Cost: $2,000. Deadline: February, 1988. Status: In progress.
7. Purchase emergency survival kits for all county offices. Cost: $125,000. Deadline: February, 1991. Status: In progress and on schedule.
8. Stockpile emergency equipment, including power saws, portable generators, air filtration masks and rescue air bags. Cost: $253,786. Deadline: February, 1990. Status: Unfunded.
9. Historic review of earthquakes and recoveries in California. Cost: $150,000. Deadline: February, 1989. Status: Unfunded.
10. Review of zoning and development laws and recommendations for any needed changes. Cost: $175,000. Deadline: February, 1988. Status: Uncertain.
11. Plan for emergency disaster information centers, Cost: $30,500. Deadline: February, 1988. Status: In progress.
12. Identify major highways, railroads, airports, dams, sanitation and utility stations and develop plan for protecting them and identifying alternatives should they fail. Cost: $140,000, Deadline: February, 1988. Status: Unfunded.
13. Evaluate state environmental building codes and any implications for this plan. Cost: None given. Status: Complete.
More to Read
Sign up for Essential California
The most important California stories and recommendations in your inbox every morning.
You may occasionally receive promotional content from the Los Angeles Times.